SG-PR-21-05 Phase 4 - Pre Mobilisation
1. Pre Mobilisation
This phase of all projects is the most important of all, at this stage all information, scopes of work and work packs must be complete to ensure that the people on site can focus on the installation progress.
Before mobilising to site, the Project Manager must be satisfied that all pre-mobilisation requirements have been met. These include:
2. Pre-Start Meeting
Immediately prior to mobilisation a pre-start meeting should be held between the Company and Client Representatives. The purpose of the pre-start meeting is to:
All Pre-start meeting’s must be minuted and follow the agenda outlined in the pre mobilization form. The purpose of this approval is to minimise the delays associated with starting construction once the crew is on site. The Pre-Mobe document must be approved by the Client Representative.
3. Project Specific Safety Management Plan
A typical project specific safety management plan will include details of the following:
3.1. Work Scope
A brief description of the work scope or reference to appropriate document
3.2. Organisation and Responsibilities
Should contain the following:
3.3. Hazard Identification
3.4. Communications
3.5. Incident Reporting
Propose to utilize Symmetrical Groups internal reporting procedure as a preference to utilizing the Clients system. In the event this is rejected the Clients system will be adopted.
3.6. Emergency Response
Request details from the client regarding their own emergency response teams and processes, document these and add any specific requirements outside Client Procedures.
3.7. Competencies
References to, or copies of all required licenses/certificates of personnel, eg:
4. Environmental Management Plan
typical project specific safety management plan will include details of the following:
4.1. Work Scope
A brief description of the work scope or reference to appropriate document
4.2. Organisation and Responsibilities
Should contain the following:
4.3. Hazard Identification
Processes to be employed on site to identify hazards:
4.4. Communications
4.5. Incident Reporting
Propose to utilize Symmetrical Groups internal reporting procedure as a preference to utilizing the Clients system. In the event this is rejected the Clients system will be adopted.
4.6. Emergency Response
Request details from the client regarding their own emergency response teams and processes, document these and add any specific requirements outside Client Procedures.
5. Compilation of Workpacks
Work packs for the completion of the works will be compiled and followed to properly install the contract scope of work. Work packs will cross over disciplines where ever necessary in order for the documentation relevant to an area to be included in one work pack.
A format for the work packs will be agreed with the Project Manager and Client Representative which will form the bench mark for all work packs going forward.
The work packs will be listed in a matrix that will have key milestones for each work pack, this matrix will be used to report the level of completion to the Client Representative and Project Manager.
6. Permission to Mobilise
When all pre-start checks and meetings have been completed the Client Representative will be advised in writing and will be asked to formally provide permission for the Company to mobilize to site (refer to Access Permission Form). A number of important steps are required once the installation crew has been finalized but before permission can be given by the Project Manager to begin mobilizing to site the following must be completed:
7. Commencing Mobilization
Once the Company has written permission to mobilise to site then preparations can be made to mobilize, the following is a list of documentation that must be supplied to the client prior to mobilizing to site:
8. Forms Relevant to this Procedure
F-HR-21 Reimburse Expenses Form
F-HR-23 Travelling Expenses Form
F-Q-01 Supplier Progress Inspection Report
F-Q-03 Corrective Action Request
F-Q-06 Piping Installation Checklist
F-Q-08 Corrective Action Request Log
F-Q-14 Archived Documents Register
F-Q-11 Customer satisfaction survey
F-Q-12 Customer service action form
F-Q-13 Internal Audit Report Form
F-G-06 Monthly Management Meeting
F-P-05 Project Roles and Responsibilities Matrix
F-M-01 Daily Co-ordination Meeting Minutes
F-M-02 Daily Pre-start Meeting Minutes
F-M-03 Project Kickoff Meeting Minutes
F-M-04 Meeting Attendance Form
F-S-01-2 Incident Notification
F-S-05 Task Planning / Risk Assessment
F-ITP-01 Comprehensive Template
F-E-01 Emergency Live Work Assessment
F-E-02 Electrical Workers Observation Form
F-E-03 Inspection and Building Test Sheet
F-ITR-15 Diff Press Tx Calibration
F-ITR-17 Gas Detector Calibration
F-ITR-23 Mechanical Completion
F-S-06 Monthly Safety Meeting Minutes
F-S-07 Daily Work Site Inspection
F-S-21-Portable_Electrical_Equipment_&_RCD_Register
F-S-22-Hazardous_Substance_Register