SG-PR-21-07 Phase 6 - Commissioning
1. Commissioning
Commissioning works may be completed in stages, with partial commissioning and takeover of works, or the whole project may be completed at once. Whatever the pathway, the first step to project completion and Client takeover is commissioning.
Commissioning involves ensuring that all required works have been completed and that components and equipment perform to acceptable levels.
A final deficiency checklist or ‘punchlist’ is developed by the Project Manager in conjunction with the Client representative. This generally involves an inspection of the site in order to determine whether work has been completed to the satisfaction of the Project Manager and the End User. Any deficiencies noted are communicated to the contractor for redress as previously noted only “A” list items will delay commissioning “B” list items will delay hand over.
2. Performance Testing and Performance
Equipment and components are run up and tested under a variety of ‘workbench’ and simulated operating conditions. Results are recorded and an assessment made by the Client Representative as to whether performance reaches acceptable levels. Any areas of unacceptable performance must be addressed.
3. Documentation
The Client must be supplied all the necessary induction, training and documentation necessary for safe and effective operation. The last stage is to bring the new equipment or work successfully online, that is, integrate it with existing processes.
All the relevant information regarding Commissioning including test results, operating or maintenance instruction documentation and any acceptance or certification documentation is provided to the client, only after being approved and signed off by the Project Manager.
Note: the nature and scale of project will determine the specific commissioning process and the type of commissioning report required.
4. Handover Requirements
Prior to submitting the final claim to the client the Project Manager must ensure the following actions have been completed and documentation is submitted to the client:
Once the commissioning of the entire project has been completed to the satisfaction of the Project Manager, the Client Representative and any key stakeholders the Project Manager completes and sends the Projects Practical Completion form.
6. Demobilisation
Once commissioning is complete and practical completion is signed off full demobilisation may commence.
7. Forms Relevant to this Procedure
F-HR-21 Reimburse Expenses Form
F-HR-23 Travelling Expenses Form
F-Q-01 Supplier Progress Inspection Report
F-Q-03 Corrective Action Request
F-Q-06 Piping Installation Checklist
F-Q-08 Corrective Action Request Log
F-Q-13 Internal Audit Report Form
F-P-05 Project Roles and Responsibilities Matrix
F-M-01 Daily Co-ordination Meeting Minutes
F-M-02 Daily Pre-start Meeting Minutes
F-M-03 Project Kickoff Meeting Minutes
F-M-04 Meeting Attendance Form
F-S-01-2 Incident Notification
F-S-05 Task Planning / Risk Assessment
F-ITP-01 Comprehensive Template
F-E-01 Emergency Live Work Assessment
F-E-02 Electrical Workers Observation Form
F-E-03 Inspection and Building Test Sheet
F-ITR-15 Diff Press Tx Calibration
F-ITR-17 Gas Detector Calibration
F-ITR-23 Mechanical Completion
F-G-06 Monthly Management Meeting
F-Q-11 Customer satisfaction survey
F-Q-12 Customer service action form
F-S-03 Weekly Work Site Inspection
F-S-04_Request for New or Alternate Chemical or Material
F-S-06 Monthly Safety Meeting Minutes
F-S-07 Daily Work Site Inspection
F-S-09- Confined Space Entry Permit_
F-S-10- Equipment Isolation Permit
F-S-21-Portable_Electrical_Equipment_&_RCD_Register
F-S-22-Hazardous_Substance_Register
Date published: 25/07/2013
Document ID: |
398 |
Last reviewed: |
13/03/2009 |
Revision No: |
7 |
Approved by: |
.. |
* -25/07/2013 12:27:06 PM